National Nuclear Safety Administration
Yangjiang NPP
2018-05-17

The Yangjiang Nuclear Power Plant is located at coastal city of Yangjiang on the western Guangdong province. With a planned total investment of 70 billion RMB, the plant houses six 1000 MW nuclear units of Chinese self-owned brand CPR1000 reactor type, with each producing 1080 MWe of electricity. Construction on Unit 1 began on 16 December 2008 with commercial operations starting on 25 March 2014, followed by Unit 2 on 4 June 2009 with commercial operations on 5 June 2015, Unit 3 on 15 November 2010 with commercial operations on 1 January 2016, and Unit 4 on 17 November 2012 with commercial operations on 15 March 2017. Construction on Unit 5 began on 18 September 2013 with the first fuel loading completed on 22 April 2018. Unit 6 began construction on 23 December 2013, currently in the stage of equipment installation and commission.

(This English version is for your reference only.In case any discrepancy exists between the Chinese and English context, the Chinese version shall prevail.)